F&C Engineers provided complete project management, engineering, and procurement support for the development of a new standardized Centralized Processing Facility for gathering production from up to 27 wells. A number of these standardized facilities are being installed to develop a large West Texas leased area. The facilities can handle 9,000 barrels of fluid per day production and 15 MMSCDF of gas. The well pads are three-well pad configurations for 1,000 bbl/day and 1000 MMSCDF wells.

Equipment included: Separators, Heater Treaters, Fuel Gas Skid, Crude Oil Storage, Gun-barrel, LACT, Truck Loading, Flare, Lift Gas Compression, Dehydration, Pig Receivers Equipment

Included in Well Pads: Test Separator, Manifold, Metering, Pig Launchers